SOHAR INDUSTRIAL PORT
CONTAINER TERMINAL B – PHASE 1
Construction of asphalt paved
area on CBM for access road and
terminal area, pre-cast block
pavings, R.C.container bases &
RTG runways, line markings,
electrical ducting & draw pits,
potable/process water & fire
fighting system, fencing and
temporary buildings for the
Client use.
Client : Oman
International Container
Terminal.
Consultant : Scott Wilson
Ltd
Contract Period: 3 ½
months
Value : RO.2.5 million |
 |
|
|
|
|
 |
SOHAR POWER & DESALINATION
PLANT
Construction of
foundations and
associated works for
1 no. steam turbine,
3 no. gas turbines,
HRSG, transformers,
evaporation units,
BRP pits, pump sets,
fuel oil storage
tanks and other
miscellaneous
equipment. Work also
includes drainage /
sewage lines and
road/pavings etc.
Client : Doosan Heavy
Industries &
Construction Co. Ltd
Consultant : Doosan Heavy
Industries &
Construction Co. Ltd
Contract Period: Main
works – 13 months
Value : RO.7 million |
|
|
|
EPC BUILDING WORKS – SOHAR
REFINERY PROJECT
This administration building is
one of 31 buildings with a total
floor area of 33,328 m2
comprising 7 no. blast resistant
plant buildings, control
building, SIH buildings, main &
process substations – admin
building, canteen, lab, training
& medical centre, mosque, fire
station, warehouse, maintenance
office/workshop &chemical
storage building etc.
Client : JGC Corporation,
Japan
Consultant : W.S.Atkins
Contract value : RO.12 m.
Contract Period: 2 years |
 |
|
|
|
 |
SOHAR ALUMINIUM POWER PLANT
Construction of foundations and
associated works for 1 no. steam
turbine, 3 no. gas turbines,
HRSG, transformers, evaporation
units, BRP pits, pump sets, fuel
oil storage tanks and other
miscellaneous equipment. Work
also includes drainage / sewage
lines and road/pavings etc.
Client : Alstom
Consultant : Alstom
Contract Period: Main
works – 13 months
Value : R14.5million |
|
|
|
SOHAR AROMATICS
Client :
Consultant :
Contract Period: Main
works – 13 months
Value : R14.5million |
|
|
BARKA POWER & DESALINATION
PLANT Phase 1
Construction of 2 No. gas
turbine foundations, 1 no. steam
turbine foundation, HRSG
boiler/stack/transformer & other
miscellaneous equipment
foundations, discharge culvert,
fire fighting pipe installation,
cable ducts, sewer lines,
earthing, building electrical
services & road works plus
electrical and instrumentation
works.
Client : Enelpower S.p.A
Consultant : Enelpower
S.p.A
Contract Period: 18
months
Value : RO.3 million |
 |
|
|
|
 |
BARKA POWER & DESALINATION
PLANT Phase 2
Due for completion 2008
Construction of 2 No. gas
turbine foundations, 1 no. steam
turbine foundation, HRSG
boiler/stack/transformer & other
miscellaneous equipment
foundations, discharge
culvert,fire fighting pipe
installation, cable ducts, sewer
lines, earthing, building
electrical services & road works
plus electrical and
instrumentation works.
Client : Doosan Heavy
Industries & Construction Co.
Ltd
Consultant : Doosan Heavy
Industries & Construction Co.
Ltd
Contract Period: 18
months
Value : RO.14 million |
|
|
|
HEADQUARTERS BUILDING FOR
G.T.O. MUSCAT, SULTANATE OF OMAN
Reinforced concrete structure
based on a series of circular
enclosures to house the nerve
centre of Oman's
telecommunications network. The
large outer sections are 30
metres high with a central tower
rising to 90 metres. External
finishes are a mixture of GRC
panels timber feature screens
and exposed wadi stone cladding.
Client: General
Telecommunication Organisation
Architect: Ayoub Oghanna
Associates
Quantity Surveyor:
Barker, Barton & Lawson
Value: RO.1 m. |
 |